The vacuum system of MAX IV storage rings : Installation and conditioning
The installation of the vacuum system of the 3 GeV storage ring was started in November 2014 and finished in May 2015. In August 2015 the commissioning of the storage ring started, the first stored beam has been achieved on the 15th of September 2015. The installation of the vacuum system of the 1.5 GeV storage ring was done from September 2015 and the main part finished in December 2015, the conn